Planning Permission Timescales

The timescale of the Planning decision process is dependent upon the validity of the application and any appeal to An Bord Pleanála.

The timescale of the decision process is dependent upon the validity and completeness of the application and the possibility of the local authority decision being subsequently appealed to An Bord Pleanála.

There is a time limit of eight weeks from when a valid application is lodged to a decision being given by the planning authority. The planning authority may issue a decision on the application (grant or refuse permission) or they may request further information.

If the Planning Authority requests further information, it has four weeks from the day the further information is received to make a decision on the application (unless the application is accompanied by an Environmental Impact Statement, in which case, the time for making a decision is extended to 8 weeks. Any appeal of the decision must be submitted within four weeks of the local authority decision to An Bord Pleanála which has an objective to decide appeals within 18 weeks of receipt.

Timescales


StageTimescaleAction
Public NoticesNotice published in newspaper and site notice erected
Receipt of application2 weeksApplication must be lodged within 2 weeks of publication of newspaper notice.
Validation1 – 5 daysApplication is validated by the planning authority as soon as possible. Current timescale is within 5 days.
Submissions5 weeksSubmissions/observations can be submitted within the first 5 weeks of receipt of application.
Notice of Decision8 weeksSubmissions/objections (submitted in first 5 weeks) are considered. Planning Authority issues notice of its decision on the application within 8 weeks of receipt of application. (Alternatively, it may request further information.)
Further Information6 monthsThe Planning Authority may request Further Information or clarification of Further Information which must be responded to within 6 months (this can be extended by 3 months at the discretion of the Planning Authority).
Notice of Decision4 weeks (8 weeks for EIS)The Planning Authority issues notice of its decision on the application within 4 weeks of receipt of the Further Information (or 4 weeks from the receipt of the public notices if Further Information is significant). (Time period is extended to 8 weeks in the case of an application accompanied by an EIS).
Appeal28 daysA decision can be appealed to An Bord Pleanála within 28 days of a decision.
Final Grant Minimum4 weeks + 3 daysIf the decision is not appealed to An Bord Pleanála, then the Planning Authority will issue a final grant of permission.